Active in City of Sacramento (6 permits)
Raw permit filing name: LEVION CONSTRUCTION LLC
4 issued · 4 parcels
vs 6 prior 24m
0 construction/remodel
Sum of permit job values
Application → issuance
Latest: Nov 15, 2023
Where this builder's geocoded permits cluster
Compares this builder's median days from permit application to issuance against all peer permits in City of Sacramento (trailing 5-year benchmark).
| Permit Category | Permits | Issued | Units | Declared Valuation | Builder Median Review | City Median (75th pct) | Relative Pace |
|---|---|---|---|---|---|---|---|
| 5 | 4 | — | $192,442 | 3d (n=4) | 3d (8d p75) | Within typical range | |
| 1 | 0 | — | — | — | 41d (93d p75) | — |
Click any address to open the full property dossier or inspect the official agency record
| Property / Parcel | Record & Category | Applied / Issued | Status | Valuation | Work Description & Raw Attribution |
|---|---|---|---|---|---|
| 3260 Northview Dr City of Sacramento · APN 262-0015-002-0000 | Plan revision / deferred submittal RES-2324375Portal ↗ | Applied Nov 15, 2023 | Complete | — | Revision to RES-2321994-11 MODULES-ROOF MOUNTED - 4.400 KW DC, 4.019 KW AC. Filed as: LEVION CONSTRUCTION LLC |
| 3260 Northview Dr City of Sacramento · APN 262-0015-002-0000 | Solar / battery storage RES-2324342Portal ↗ | Applied Nov 14, 2023 | Withdrawn | $40,152 | 4.4kw Solar PV System, and 0gal Solar WH System (water heater installed null). All supply side connections, main breaker change-out, and/or panel upgrade will require a second inspection. Carbon monoxide & Smoke alarms required. Reference CRC sections R315 & R314, Water conserving fixtures are required to be installed throughout this residence per SB 407 (Note: Residences built after January 1, 1994 are exempt).” Filed as: LEVION CONSTRUCTION LLC |
| 3260 Northview Dr City of Sacramento · APN 262-0015-002-0000 | Solar / battery storage RES-2321994Portal ↗ | Issued Oct 18, 2023 2d review | Expired Permit | $40,152 | 4.4kw Solar PV System, and 0gal Solar WH System (water heater installed null) (N) 240V/200A SUB PANEL .All supply side connections, main breaker change-out, and/or panel upgrade will require a second inspection. Carbon monoxide & Smoke alarms required. Reference CRC sections R315 & R314, Water conserving fixtures are required to be installed throughout this residence per SB 407 (Note: Residences built after January 1, 1994 are exempt). Revision RES-2324375-Changed to 11 MODULES-ROOF MOUNTED - 4.400 KW DC, 4.019 KW AC. Filed as: LEVION CONSTRUCTION LLC |
| 2364 North Ave City of Sacramento · APN 252-0041-009-0000 | Solar / battery storage RES-2311991Portal ↗ | Issued Jun 16, 2023 4d review | Finaled | $43,622 | 5.20kw Solar PV System, and 0gal Solar WH System (water heater installed null). All supply side connections, main breaker change-out, and/or panel upgrade will require a second inspection. Carbon monoxide & Smoke alarms required. Reference CRC sections R315 & R314, Water conserving fixtures are required to be installed throughout this residence per SB 407 (Note: Residences built after January 1, 1994 are exempt). Filed as: LEVION CONSTRUCTION LLC |
| 3017 Occidental Dr City of Sacramento · APN 079-0132-002-0000 | Solar / battery storage RES-2308165Portal ↗ | Issued Apr 25, 2023 0d review | Finaled | $28,625 | 4.4kw Solar PV System, and 0gal Solar WH System (water heater installed null). Roof mounted, 11 modules, 11 micro inverters, 125A combiner, existing main service panel. Water conserving fixtures are required to be installed throughout this structure per SB 407 (Note: Residences built after January 1, 1994 are exempt). Carbon monoxide & Smoke alarms required. Reference 2022 CRC sections R315 & R314. ALL WORK SUBJECT TO FIELD INSPECTION. Filed as: LEVION CONSTRUCTION LLC |
| 6061 39th Ave City of Sacramento · APN 027-0281-012-0000 | Solar / battery storage RES-2306646Portal ↗ | Issued Apr 17, 2023 12d review | Finaled | $39,890 | 5.46kw Solar PV System,w/ MPU and 0gal Solar WH System (water heater installed null). All supply side connections, main breaker change-out, and/or panel upgrade will require a second inspection. Carbon monoxide & Smoke alarms required. Reference CRC sections R315 & R314, Water conserving fixtures are required to be installed throughout this residence per SB 407 (Note: Residences built after January 1, 1994 are exempt).” Filed as: LEVION CONSTRUCTION LLC |