Retired / historical parcel number
Recorded at 400 Jibboom St · Records from 2016–2020
Operable Partition
EPC - Deferred to COM-1811608, Approval documentation for the Operable Partition at the Powerhouse Science Center Museum
Revision
EPC - Revision to Issued Permit COM-1811608 - Plans for ASI 041 which is a revision to COM-1811608. The scope adds Exhibit and Education office (B211) spaces and Small Conference (B212) at the north west end of the turbine room. This document also adds the Design Classroom (B210) to the north end of the turbine room.
Revision
Revision to Issued Permit COM-1811608 - Plans for ASI 041 which is a revision to COM-1811608. The scope adds Exhibit and Education office (B211) spaces and Small Conference (B212) at the north west end of the turbine room. This document also adds the Design Classroom (B210) to the north end of the turbine room.
Curtain Wall
EPC - Deferred to Issued Permit COM-1811608 - Deferred Approval Document for the Aluminum Curtainwall for the new building at the Powerhouse Science Center as noted on the cover page for the primary permit documents. This package also contains drawing/calculation for the aluminum entrances and storefront which is crossed out, and will be submitted under DA #005
Storefront
EPC - Deferred to Issued Permit COM-1811608 - Deferred Approval Document for the Aluminum Entrances and Storefront for the new building at the Powerhouse Science Center as noted on the cover page for the primary permit documents. This package also contains drawing/calculation for the Curtainwall, it is crossed out, and will be submitted under DA #006
Curtain Wall
Deferred to Issued Permit COM-1811608 - Deferred Approval Document for the Aluminum Curtainwall for the new building at the Powerhouse Science Center as noted on the cover page for the primary permit documents. This package also contains drawing/calculation for the aluminum entrances and storefront which is crossed out, and will be submitted under DA #005
Storefront
Deferred to Issued Permit COM-1811608 - Deferred Approval Document for the Aluminum Entrances and Storefront for the new building at the Powerhouse Science Center as noted on the cover page for the primary permit documents. This package also contains drawing/calculation for the Curtainwall, it is crossed out, and will be submitted under DA #006
Power House
EPC - Revision to Issued Permit COM-1803505 - revise the base plate height and support at grid line E4 along grid line EH at the first floor of the existing building. Additional revisions in ASI 042 provide connection of steel beams at (4) places along the south wall at grid line E1 at the roof of the building. See attached ASI cover sheet for additional information.
Power House
Revision to Issued Permit COM-1803505 - revise the base plate height and support at grid line E4 along grid line EH at the first floor of the existing building. Additional revisions in ASI 042 provide connection of steel beams at (4) places along the south wall at grid line E1 at the roof of the building. See attached ASI cover sheet for additional information.
Power House
EPC - Deferred to Issued Permit COM-1811608 - Deferred Approval document (DA-004) for the Powerhouse Science Center Addition Building (COM-1811608) which is the aluminum projection dome (inner dome) for the Planetarium at the Powerhouse Science Center.
Power House
Deferred to Issued Permit COM-1811608 - Deferred Approval document (DA-004) for the Powerhouse Science Center Addition Building (COM-1811608) which is the aluminum projection dome (inner dome) for the Planetarium at the Powerhouse Science Center.
Power House
EPC - Revision to COM-1803505 - ASI 019 is a revision to the exhibit space 100 and 105 on the first floor to allow for the future installation of the Water and Nature Exhibits. The revision includes moving two floor sink locations and adding infrastructure for future power/data outlets in the walls to be installed under separate permit.
Power House
Deferred to Issued Permit COM-1811608 - Revision document submittal of (ASI-027) which makes minor revisions to the location of elevator support steel based on review of Shop Drawings. Additional changes include revision of waterproofing system under slab at elevator pit.
Power House
Source: City of Sacramento CDD, Issued Building Permits (Current Year) · Geography: parcel (APN as recorded on the permit) · Source updated Oct 1, 2026 · Retrieved Oct 22, 2026 · The city publishes current status without a date, so status changes are dated by the window between our snapshots.
APN 001-0190-020-0000 · 42 permits matched by address and location
Matched by checking which current parcel holds each permit's mapped point, or carries its street address. This is our inference, not an official County lineage record.
Source: Sacramento County GIS, Parcels · Geography: current parcel polygons · Source updated Oct 25, 2026 · Retrieved Oct 25, 2026
Assessed values and limited building characteristics (Sacramento County Assessor)
Search by parcel number 001-0190-004-0000. Shows direct levies and special assessments.
Search the city's permit system by address or record number
County systems may not return results for a retired number. If so, use a current parcel listed above. Most recent record here: Mar 18, 2020.
Deferred to Issued Permit COM-1811608 - The scope of work for this Deferred approval is to install the elevator, shop drawings showing the support steel and attachment for the elevator guide rails, at the Powerhouse Science Center, New Addition project (COM-1811608).
Power House
EPC - Deferred to Issued Permit COM-1811608 - The scope of work for this Deferred approval is to install the elevator, shop drawings showing the support steel and attachment for the elevator guide rails, at the Powerhouse Science Center, New Addition project (COM-1811608).
Power House
EPC - Revision to Issued Permit COM-1811608 - Revision document submittal of (ASI-027) which makes minor revisions to the location of elevator support steel based on review of Shop Drawings. Additional changes include revision of waterproofing system under slab at elevator pit.
Power House
Revision to COM-1803505 - ASI 019 is a revision to the exhibit space 100 and 105 on the first floor to allow for the future installation of the Water and Nature Exhibits. The revision includes moving two floor sink locations and adding infrastructure for future power/data outlets in the walls to be installed under separate permit.
REVISION - ASI-24
EPC - REVISION TO COM-1811608 - Various Steel detailing revisions based on review of the Structural Steel Subcontractor steel submittal.
REVISION - Bulletin IB-F
EPC - REVISION TO COM-1811608. The scope of work of IB-F is to revise the location of the FDC and PIV, to match the location requested by City of Sacramento Fire Department. Additionally, revise the height of the Tilt Panel at the elevator shaft and add a 20" wide stemwall under the panel.
REVISION - Structural
EPC - REVISION TO COM-1803505. This revision includes structural steel support under and wind beams along grid lines E1 and E8. Increase of wall thickness from 12" to 14" to accommodate shoring columns. Add rebar to the base of the column to lap with the vertical bars in the concrete encasement. Allow slab section between basement wall and first floor to remain.
EPC Submittal - Deferred/Revision to Issued Permit COM-1811608 - Various Steel detailing revisions based on review of the Structural Steel Subcontractor steel submittal.
EPC Submittal - Deferred/Revision to Issued Permit COM-1803505 - This revision includes structural steel support under and wind beams along grid lines E1 and E8. Increase of wall thickness from 12" to 14" to accommodate shoring columns. Add rebar to the base of the column to lap with the vertical bars in the concrete encasement. Allow slab section between basement wall and first floor to remain.
EPC Submittal - Deferred/Revision to Issued Permit COM-1811608 - The scope of work of IB-F is to revise the location of the FDC and PIV, to match the location requested by City of Sacramento Fire Department. Additionally, revise the height of the Tilt Panel at the elevator shaft and add a 20" wide stemwall under the panel.
Power House
EPC Submittal - Deferred to Issued Permit COM-1803505 - Deferred Approval documentation for the Drilled Pipe Piles under the existing powerhouse building.
Power House
EPC Submittal - Deferred to Issued Permit COM-1803505 - Deferred Approval documentation for the Drilled Pipe Piles under the existing powerhouse building.
Power House
EPC - Revision to Issued Permit COM-1803505 - Additional Structural steel design, required as unforseen conditions were exposed during Demolition Work
Power House
EPC - Deferred to Issued Permit COM-1811608 - Deferred Approval Documentation for installation of Drilled Pipe Piles (micro-piles) at the southwest corner of the Powerhouse Science Center expansion building
Power House
Deferred to Issued Permit COM-1811608 - Deferred Approval Documentation for installation of Drilled Pipe Piles (micro-piles) at the southwest corner of the Powerhouse Science Center expansion building
Power House
EPC - Deferred to Issued Permit COM-1811608 - Deferred Approval documentation for the Drill Displacement Piles at the Main building package
Power House
Deferred to Issued Permit COM-1811608 - Deferred Approval documentation for the Drill Displacement Piles at the Main building package
Power House
Revision to Issued Permit COM-1803505 - Additional Structural steel design, required as unforseen conditions were exposed during Demolition Work
Power House
Revision to Issued Permit COM-1811608 - Add 20" wide CIP Concrete wall at the elevator pit to facilitate constructability and waterproofing. Install the tilt-up Concrete wall approximately 12" below first floor level as shown on details.
Power House
EPC - Civil changes to the fire hydrant tap, manhole, and install a sewer cleanout. Revision to COM-1811608, Addition to Commercial Building - The permit package is for the Main Construction package for the Powerhouse Science Center. The Addition square footage is 21,440.The scope of work includes site: lighting utilities, grading and drainage, etc. The permit package is for the Main Construction package for the Powerhouse Science Center. The scope of work includes site: lighting utilities, grading and drainage, etc.Interior Build Out: interior partitions, ceiling systems, mechanical distribution, interior lighting, electrical power distribution, plumbing fixtures, AV, fire alarm and fire protection, signage, etc. $4.6M valuation is for the remainder of the renovation. See permit COM-1803505 for the additional scope of work. The DEFERRED ITEMS are Curtain Wall/Storefront Systems, Planetarium Projection Dome, Interpretive Historic Smokestack, Elevator, Piles, Sunshades, Operable Partition - PLNG-INSP
Power House
EPC Submittal - Addition to Commercial Building - The permit package is for the Main Construction package for the Powerhouse Science Center. The Addition square footage is 21,440.The scope of work includes site: lighting utilities, grading and drainage, etc. The permit package is for the Main Construction package for the Powerhouse Science Center. The scope of work includes site: lighting utilities, grading and drainage, etc.Interior Build Out: interior partitions, ceiling systems, mechanical distribution, interior lighting, electrical power distribution, plumbing fixtures, AV, fire alarm and fire protection, signage, etc. $4.6M valuation is for the remainder of the renovation. See permit COM-1803505 for the additional scope of work. The DEFERRED ITEMS are Curtain Wall/Storefront Systems, Planetarium Projection Dome, Interpretive Historic Smokestack, Elevator, Piles, Sunshades, Operable Partition - PLNG-INSP
Power House
EPC - Revision to Issued Permit COM-1803505 - Revisions to the infill of the south opening, revisions to the stair, addition of the banner system, revisions to mechanical louver in roof monitor, and revisions to misc structural, mechanical and plumbing elements.
Power House
Revision to Issued Permit COM-1803505 - Revisions to the infill of the south opening, revisions to the stair, addition of the banner system, revisions to mechanical louver in roof monitor, and revisions to misc structural, mechanical and plumbing elements.
TEMP POWER POLE 200A
Install temporary power pole for construction power only. Not intended or to be used for energizing a construction trailer (separate permit would be required)
Power House
EPC - Remodel Power Station B building as a cold shell. The scope of work includes removal of floor and roof which has been deemed unsafe. Installation of new foundation, new floor, and roof. Stabilization and repair of the existing exterior concrete wall. A weather tight envelope to prevent further deterioration. The scope of work also includes the installation of new stairs, the second floor, rough grading of the site, below slab rough-in for plumbing and electrical systems. It is not the intent of this scope of work to result in an occupied building therefore does not include measures for life safety or fire protection. Those measures will be included in the main building package to be submitted separately. - PLNG-INSP
Power House
EPC Submittal - Addition to Commercial Building - The permit package is for the Main Construction package for the Powerhouse Science Center. The scope of work includes site: lighting utilities, grading and drainage, etc. The permit package is for the Main Construction package for the Powerhouse Science Center. The scope of work includes site: lighting utilities, grading and drainage, etc.Interior Build Out: interior partitions, ceiling systems, mechanical distribution, interior lighting, electrical power distribution, plumbing fixtures, AV, fire alarm and fire protection, signage, etc. $4.6M valuation is for the remainder of the renovation.
Power House
EPC Submittal - Remodel of Commercial Building - The permit package includes all work to structurally stabilize and provide a weather tight envelope for the Power Station B building. The package also includes rough grading for the site, any below slab rough-in for plumbing and electrical systems to be installed in the main building package. It is not the intent of this scope of work to result in a building meant for occupancy. This package does not include measures for life safety.
POWER HOUSE SCIENCE CENTER - FEE ESTIMATE
EPC - FEE ESTIMATE - Renovation of the historic PG&E Power Station Building {34,282 sqft. remodel/17,618 sqft. addition} for a new Earth and Space Science Center Museum. Breakdown of areas: BASEMENT consist of: 1,300 sqft new basement addition & 13,900 sqft. of existing basement; 1ST FLOOR consist of: 4,018 sqft. of a new pavilion entrance addition & 13,682 sqft of renovated area; 2ND FLOOR consist of: 3,800 sqft of renovated area for office formally a mezzanine; and 12,300 sqft addition for new exhibit areas and a 36’ high planetarium dome; and 3RD FLOOR consist of: 2,900 sqft of renovated area for office formally a mezzanine. - PLNG-INSP
POWER HOUSE SCIENCE CENTER - FEE ESTIMATE
EPC - FEE ESTIMATE - Renovation of the historic PG&E Power Station Building {34,282 sqft. remodel/17,618 sqft. addition} for a new Earth and Space Science Center Museum. Breakdown of areas: BASEMENT consist of: 1,300 sqft new basement addition & 13,900 sqft. of existing basement; 1ST FLOOR consist of: 4,018 sqft. of a new pavilion entrance addition & 13,682 sqft of renovated area; 2ND FLOOR consist of: 3,800 sqft of renovated area for office formally a mezzanine; and 12,300 sqft addition for new exhibit areas and a 36’ high planetarium dome; and 3RD FLOOR consist of: 2,900 sqft of renovated area for office formally a mezzanine. - PLNG-INSP