Retired / historical parcel number
Recorded at 500 David J Stern Walk; 609 L St · Records from 2016–2019
ESC - NEW ARENA AND PRACTICE FACILITY
EPC - EXPEDITED - NEW ARENA AND PRACTICE FACILITY - construction of 754,509 (64,245 existing parking to remain at parking levels 1 & 2) sqft arena and practice facility on 6.8 acres in the downtown plaza. - PLNG-INSP
REVISION TO COM-1512181 - FIRE ALARM
REVISION TO COM-1512181 - FIRE ALARM Revision to the approved fire alarm system to remove a beam detector on the catwalk level inside of the G1C due to new signage installed above the video board..
REVISION - FIRE SPRINKLERS
EPC - Revision to (main permit COM-1504712) approved fire sprinklers for the G1C to add additional sprinkler coverage to retractable seating (to allow storage) currently located below the precast stadia at Event Level (sheets FP EL 03, 04 & 05).
REVISION - Storm & Sewer Lines
EPC - Revision (COM-1415518) to update drawings for the 18" storm and 10" sewer lines for cleanouts beneath the Plaza at the G1C site.
REVISION - Occupant Load Increase
EPC - Revision to (COM-1415518) add "standing room only" capacity (648 additional ticketed patrons) at the letter box end of the Bridge Level (upper concourse) in the Golden 1 Center.
REVISION - Occupant Load @ Box Office Lobby
EPC - Revision (COM-1415518) to modify the occupant load at the Box Office Lobby in the Arena
REVISION - SUPPORT ART WORK
EPC - Revision (COM-1415518) to add support framing for artwork at upper concourse in the Arena
MOBILE GRILL EQUIPMENT
EPC - Installation of 6 mobile grill units in the Arena - includes installation of the pull stations for the grills
DAS EQUIPMENT RACKS - DATA ROOM
EPC - Installation of (12) DAS equipment racks in the DAS Headend Comm. Room as well as coax cable support structure. Adding thirteen (14) 20A breaks to the existing 400A panel and pull electrical to feed thirteen (13) 20A outlets for powering the equipment racks.
Bridge Lift Support System
EPC - Bridge Lift Support System (rigging/truss) for the installation of lapidaries above the halo in the upper bowl of the Arena
REVISION - FIRE ALARM ASPIRATION
EPC - Revision (COM-1512181) to fire alarm to install fire alarm aspiration systems in the Arena.
VERIZON - DAS EQUIPMENT
EXPEDITED - EPC - Installation of Wireless Verizon equipment: to include radio cabinet, remote radio heads, battery and power bay and GPS installation with the required RF,DC and Data Cabling - PLNG-INSP
REVISION - PLAZA STAIR RELOCATION
EPC - Revision (COM-1508618) to Plaza work immediately in front of 630 K to relocate stairs constructed by Turner Construction.
REVISION - Plaza Work (Phases 3 and 7)
Source: City of Sacramento CDD, Issued Building Permits (Current Year) · Geography: parcel (APN as recorded on the permit) · Source updated Nov 1, 2026 · Retrieved Nov 3, 2026 · The city publishes current status without a date, so status changes are dated by the window between our snapshots.
APN 006-0370-012-0000 · 80 permits matched by address and location
APN 066-137-010-6 · 2 permits matched by address
Matched by checking which current parcel holds each permit's mapped point, or carries its street address. This is our inference, not an official County lineage record.
Source: Sacramento County GIS, Parcels · Geography: current parcel polygons · Source updated Nov 15, 2026 · Retrieved Nov 15, 2026
Assessed values and limited building characteristics (Sacramento County Assessor)
Search by parcel number 006-0087-033-0000. Shows direct levies and special assessments.
Search the city's permit system by address or record number
County systems may not return results for a retired number. If so, use a current parcel listed above. Most recent record here: May 17, 2019.
EPC - Revision (COM-1508618) to Plaza work to remove Phases 3 and 7 construction from the overall Plaza work. This permit re-defines the actual Plaza area to be constructed by Turner.
REVISION - Plaza Work (Phase 7)
EPC - REVISION (COM-1508618) to Plaza work for Phase 7 work to be constructed by Swinerton Builders as part of mixed use commercial/hotel work currently under construction.
DAS EQUIPMENT RACKS - DATA ROOM
EPC - Installation of (12) DAS equipment racks in the DAS Headend Comm. Room as well as coax cable support structure. Adding thirteen (14) 20A breaks to the existing 400A panel and pull electrical to feed thirteen (13) 20A outlets for powering the equipment racks.
ESC - Signage Support Systems
EPC - Signage Support systems for interior way finding signage only (anchorage with engineering calculations) for the Arena and Practice Facility.
ESC - Revision to Mechanical System
EPC - Revision to (COM-1415518) mechanical systems in two concession areas in the Arena
ESC - Revision Clean Agent Fire Extinguishing Systems
EPC - Revision to (COM-1603994) the Clean Agent Fire Extinguishing Systems (to reflect as-built dimensions & locations) at the Arena/Practice Facility
ESC - Conduits for Speaker Wires
EPC - Installation of conduit (1 - 4" run) only for speaker wires to be located in parking level 2 for the Fontana sound art in the Plaza. The conduit will be exposed on the garage ceiling
AT&T TELECOM EQUIPMENT
EPC - Installation of new AT&T Telecom equipment racks inside of an existing vacant room at the lower mezzanine level in the Arena building (1170 sqft area)
DEFERRED - STRUCTURAL SUPPORTS
EPC - Deferred (COM-1415518) for installation of support structures that hang from the ceiling and loft bridges above the Main Concourse to support TV’s.
REVISION - ELECTRICAL/MECHANICAL
EPC - Revision (COM-1415518) to revise electrical and mechanical, installation of backing for future mercantile tenant improvements in the Arena.
REVISION - Stair Rating (stair 6)
EPC - Revision (COM-1415518) to eliminate the stair rating at Stair 6 in the Lower Mezzanine - Level D at the Arena
BLADE SIGN - STRUCTURAL CAL'S
EPC - Deferred submittal (COM-1415518) for structural supports of the G1 blade sign at the west elevation on 5th Street 7.10)
ESC - FIRE SPRINKLERS
EPC - Revision To COM-1504712 Changes made based on AHJ comments/as-built conditions at Event Level B/C and Practice Facility Upper Parking. FIRE SPRINKLERS for the ARENA AND PRACTICE FACILITY buildings and parking levels associated with the buildings (REVISION #6)
REVISION - PLAZA WORK
EPC - Revision (COM-1508618) for various work under construction within the Plaza area to be performed by Swinterton Builders as part of JMA's mixed use project
REVISION - MAIN BUILDING
EPC - Revision (COM-1415518) in the Arena building for Event Level Club occupancy numbers
ESC - ADD SUSPENDED T-BAR CEILING
EPC - Addition of a new suspended T-bar ceiling at the Event Level
1st TIME TENANT IMPROVEMENT - RETAIL SPACES
EPC - 1st Time Tenant Improvement for various retail spaces (7000 sqft. total) throughout the Arena and Practice Facility. Retail spaces will be located on the Main Concourse, Upper Concourse, Suite Level & Practice Facility.
REVISION - STRUCTURAL
EPC - Revision (COM-1415518) for structural sign supports for Vintage Signage on the main concourse (wall mounted) in the Arena.
REVISIONS - Fanatics Retail
EPC - Revision (COM-1415518) to fanatics retail build-out in the Arena.
REVISION - Electrical
EPC - Revision (COM-1415518) for miscellaneous electrical circuiting in the Arena.
DEFERRED - Signage Support Details (roof)
EPC - Deferred (COM-1415518) submittal for lighting and the power and structural supports for lights on the roof (future sign to be painted on roof). This permit does not include sign for permit
DEFERRED - FALL PROTECTION SYSTEMS
EPC - Deferred (main permit COM-1415518) submittal for installation of Fall Protections Systems (data and cut-sheets) at the Arena building
REVISION - ELECTRIAL CIRCUITS & MOTOR LOADS
EPC - Revision (COM-1415518) for motor loads and electrical circuit panels to service the retractable seating in the Arena
DEFERRED - SEISMIC BRACING
EPC - Deferred (COM-1415518) submittal for seismic bracing of the 18" DSW and 10" SS pipe (shop drawings and calculations)
REVISION - ADD CEILING (EVENT LEVEL)
EPC - Revision to (COM-1415518) add ceiling at the Event Level
ESC - FIRE SPRINKLERS REVISIONS (PART 2)
EPC - REVISIONS (COM-1504712) to approved Fire Sprinklers set to install fire sprinklers at the Practice Facility and Arena (plan sheets for review, clarity to inspectors and a result of work completed in field).
ESC - Art Work - Terrazzon & Dart (4)
EPC - Art work Dart & Terrazzo Dart (4) - (12' tall by 16" wide) mount plate and dart in public right of way adjacent to new Arena on L Street. - PLNG-INSP
REVISION - WALL RATING
EPC - Revision (main permit COM-1415518) to remove unnecessary wall rating at a storage room on the Event Level at the Arena.
ESC - Art Work Terrazzon & Dart(3)
EPC - Art work Dart & Terrazzo Dart (3) - (12' tall by 16" wide) mount plate and dart in public right of way adjacent to new Arena on L Street.
ESC - Art Work Dart & Terrazzo Dart (2)
EPC - Art work Dart & Terrazzo Dart (2) - (12' tall by 16" wide) mount plate and dart in public right of way adjacent to new Arena on L Street.
ESC - Art Work Bronze Hand Sculpture
EPC - Art work Bronze Hand (9' x 4') to be installed in the planter at the 5th Street and L Street entrance on the foothill terrace.
ESC - Deferred Submittal
EPC - Deferred submittal (Main - COM-1415518) to install seismic controls for the electrical systems at the transformer.
ESC - DEFERRED - Stair in Upper Bowl
EPC - Deferred submittal (COM-1415518) to install a stair in the Upper Bowl Control Room at the Arena.
ESC - NEW ELECTRICAL ROOM
EPC - Construction of a new electrical room (232 sf) in the parking garage beneath the Practice Facility
ESC - DEFERRED SUBMITTAL
EPC - Deferred submittal (main permit COM-1415518) to install Structural Supports, Rigging Drawings, and Calculations for the Arena/Practice Facility Speaker Cluster and Bowl Speakers
ESC - REVISION
EPC - Revision to (COM-1415518) two bars on the Upper Concourse level inside of the Arena
ESC - DEFERRED SUBMITTAL
EPC - Deferred submittal (COM-1415518) for Seismic Controls for Plumbing Systems within the Practice Facility Parking Garage
ESC - REVISION - FIRE ALARM SYSTEM
EPC - Revision to a deferred submittal (COM-1512181) for the digital addressing for the Fire Alarm System in the Arena and Practice Facility.
ESC - ELECTRICAL REVISION
EPC - Revision (COM-1415518) to change to power distribution for datacenter in the Arena
ESC - REVISION PLAZA
EPC - Revision (COM-1508618) to install double planter walls, planters and stairs on the northeast portion of the Plaza (K Street/24hr. Fitness area {sheet AS-03-05) DAS/WIFI access antennas throughout plaza area. Wayfinding signs are not part of this revision, only the foundation and electric stubs.
ESC - REVISION ELECTRICAL
EPC - Revisions (COM-1415518) to change the electrical equipment (replacement of one medium voltage switch)
ESC - KITCHEN HOOD ANSUL SYSTEM
EPC - Deferred submittal (COM-1415518) to install the Kitchen Hood Ansul System (shop drawings).
DEFERRED SUBMITTAL - EXTERIOR BLADE SIGNS
EPC - Deferred (COM-1415518) submittal for the review of shop drawings and calculations for Blade Signs on the exterior of the arena building.
DEFERRED - Retractable Seating
EPC - Deferred (COM-1415518) submittal to install retractable prefabricated metal seating in the Arena facility
DEFERRED - Riser Platforms
EPC - Deferred Submittal (COM-1415518) for riser platforms in the Arena
REVISION - VIDEO BOARD SUPPORT SYSTEMS
EPC - Revision (COM-1415518) to main permit packet to provide electrical power for the Panasonic Video Boards (submitted under a deferred packet - COM-1603346). Structural and Electrical sheets.
REVISION - Wall Removal
EPC - Revision (COM-1415518) for removal of a portion of fire rated wall (at gird line R11.5) @ Upper Concourse
ESC - VALENZULA ART WORK
EPC - Valenzula Art Work - Glass spheres suspended from the upper concourse within the Arena complex.
REVISION - Plaza Drawings for Koons Sculpture
EPC - Revision (COM-1508618) to landscape/plaza drawings & structural calculations for the Koons Sculpture Base on the Plaza
REVISION - Wall Ratings
EPC - Revision (COM-1415518) to clarify wall ratings at Event Level
DEFERRED - Refer Piping
EPC -Deferred (main permit COM-1408554) Food Service Refer piping
REVISION - STRUCTURAL STEEL
EPC - Revision to structural steel to accommodate future signage
DEFERRED SUBMITTAL
EPC - Deferred (main permit - COM-1408554) submittal for Exterior Chevron Glass @ main entry of Arena
DEFERRED - CLEAN AGENT SYSTEMS
EPC - Deferred - Clean Agent Systems - Arena
REVISION - STAIR 3 BEAMS/STAIRS
EPC - Revision (COM-1415518) to change from SFRM to intumescent paint on some of the beams in Stair 3 to satisfy code-required clearances.
REVISION - UPPER CONCOURSE/FRAMED CEILING
EPC - Revision (COM-1515418) shop drawings and calculations for the Upper Concourse Framed Ceiling at the Main Entry
ESC - Gale Hart's Art Work (Dart 1)
EPC - Dart 1 Art Work to be installed on L Street, at the 5th Street entrance on the foothill terrace. The dart is roughly 12 feet high mounted on a base plate. - PLNG-INSP
DEFERRED SUBMITTAL
EPC - Deferred submittal (main permit COM-1408554) for Seismic Controls for Mechanical Systems - Sheet Metal Shop Drawings
LED PANASONIC VIDEO BOARDS - DEFERRED SUBMITTAL
EPC - LED PANASONIC VIDEO BOARDS - OUTSIDE AND INSIDE OF THE ARENA/PRACTICE FACILITY
REVISION - FIBER REINFORCEMENT
EPC - Revision to (COM-1515518) to add Fiber Reinforced Polymer Strengthening for holes drilled in Practice Facility slab
REVISION - VENTLESS GAS PRESSURE REGULATOR
EPC - Revision to (COM-1415518) to install Natural Gas Systems - Vent less Gas Pressure Regulator in the Arena/Practice Facility
ESC - REVISION - ELECTRICAL
EPC - Revision (COM-1415518) to relocate circuiting (in-floor electrical & low voltage) to floor box at the scoring table on the event level.
REVISION - Rated Conditions Under Stadia Air Plenums
EPC - Revision to (COM-1415518) rated conditions for various walls under stadia air plenums
DEFERRED SUBMITTAL - HANDRAILS
EPC - Deferred submittal (main permit COM-1408554) for shop drawings and product data for the Exterior Arena Glass Handrails at the corner of 5th and L Streets
REVISION - Electrical Plans
EPC - Revision to the approved electrical plans to depict details for how electrical components will comply with the approved AMMR #5 (Public Address System).
ESC - LANDSCPE PLAZA W/ARENA & PRACTICE FACILI
EPC - LANDSCAPE PLAZA W/New Arena and Practice Facility - construction of the new plaza adjacent to arena and practice facility in downtown plaza. - PLNG-INSP
REVISION - HIGH ROOF/CATWALK
EPC - Revisions to COM-1510807 (Deferred Submittal) to relocate seismic braces to the High Roof/Catwalk